Stick vs Unitised Curtain Wall

For facade contractors, engineers and estimators

Stick and unitised (unitized) curtain walls differ in where the wall is built. A stick system is assembled and glazed on the building from mullions and transoms; a unitised system arrives as factory-assembled, glazed panels that are hung floor by floor. Onos fabricates stick members and assembles unitised panels for facade contractors and main contractors in Dubai and across the UAE.

System data below is quoted from the system houses, with links, and describes tested configurations rather than project guarantees. Durations and rates depend on the building, so none are given.

Looking up at a glass curtain wall grid against a pale sky

What is a stick curtain wall?

A stick curtain wall is built on the building, piece by piece. The facade contractor anchors mullions to the slab edges, fixes transoms between them, then glazes and seals the glass and spandrel panels into that grid on site.

Typical stick series include Schüco FWS 50, with a 50 mm face width and mullion depths of 50 to 250 mm, and Reynaers ConceptWall 50, with a 50 mm face and mullion depths of 42 to 300 mm (technical information). Both houses also publish 60 mm face versions, FWS 60 and ConceptWall 60; Reynaers positions the latter for higher wind-load areas.

The strength of a stick system is flexibility. Members are cut and machined to the shop drawings, but the final fit happens against the built structure, so irregular geometry, small elevations and late interface changes are easier to absorb.

Curved unitised glass curtain wall with dark mullions against a clear sky

What is a unitised curtain wall?

A unitised curtain wall is assembled and glazed in a factory as complete panels, usually one storey high and one grid module wide. On site, each unit is lifted, hung on brackets fixed to the slab edge and interlocked with the units beside and below it, so the building is closed in floor by floor.

Schüco describes unitised facades as moving value creation from the building site to the production hall (Schüco facades). Its AF UDC 80 unitised system uses brackets adjustable along three axes and a saddle gasket that joins the units; the AF UDC 80 SG data gives an 80 mm face width and units of up to 3,000 × 4,000 mm and 1,000 kg.

Reynaers lists ElementFaçade 7 as an off-the-shelf unitised system with a 75 mm face and a straight-cut variant, and positions ConceptWall 86 as a unitised system for large projects. Inoform Systems lists the F80 and F9M modular curtain walls. We fabricate all three ranges; see systems.

Stick and unitised compared

A unitised versus stick system comparison comes down to where the work happens. This is what that changes on a tender.

CriterionStick systemUnitised system
Where it is builtOn site, member by member, then glazed in placeIn a factory, as complete glazed units
Site labourHigher: assembly, glazing and sealing at heightLower: units are hung and interlocked
Access and liftingScaffold or platforms along each elevation; light loads hoistedCrane or hoist time for every unit; less facade scaffold
Site conditionsGlazing and sealing done in site heat, dust and humidityGlazing and sealing done indoors; site work is mostly hanging
Engineering before siteLess; details can follow the structureMore: units, brackets, joints and drainage fixed before production
Aluminium contentOne mullion per grid lineSplit mullions and transoms where units meet
Fit to the structureAdjusted member by member against the built structureTaken up at adjustable brackets; slab edges surveyed by the contractor before production
MovementTaken up in the grid joints and anchorsTaken up in the interlocking joints between units
LogisticsCompact profile bundles and loose glassBulky units on stillages; storage and floor-by-floor delivery
Usual fitLow-rise, podiums, irregular or small elevationsRepetitive mid- and high-rise elevations, tight site programmes

Neither route is better in general. Unitised spends more on engineering and factory work to save site time and labour; stick spends less up front and does more of the work at height. Height, repetition, site access and programme usually decide.

Programme and cost drivers

On site, unitised is generally faster: units arrive glazed and each floor closes in one lift-and-hang operation, with less labour at height. The whole programme is not automatically shorter, because unit design, approvals, any specified mock-up and factory production must all be complete before the first unit lands.

Stick starts on site sooner with less up-front engineering, but more labour sits at height and in the weather. The Dubai Building Code design conditions include up to 48 °C in the shade, relative humidity up to 100% and sandstorms (DBC 2021, Table G.3), which matter most where glazing and sealing happen outdoors.

We do not publish rates. We price a curtain wall package from the drawings and BOQ, and these are the drivers that move it:

  • Fabrication content: unitised moves assembly and glazing into the factory and uses split mullions, so the supply package is larger even as site labour falls.
  • Repetition: unitised pays back on repeated unit types; many one-off units erode the production-line benefit.
  • Site labour and access: stick needs more installer hours and longer scaffold time; unitised needs crane or hoist time, handling frames and set-down space.
  • Engineering: unit joints, brackets and drainage are designed up front and are often proven on a mock-up before production.
  • Glass and finish: glass make-up, heat soaking and coating class drive cost in both routes.
  • Logistics: unitised needs stillages, storage and delivery by floor; stick ships compact bundles but more loose parts to track.

Testing and mock-ups

Performance and testing are set by the project specification and the facade engineer, not by the build route. Where a performance mock-up or site tests are specified, the facade contractor commissions them. On a unitised wall the mock-up carries more weight, because it proves the unit joints and drainage that repeat across the building. System houses publish type-test results for each series, and those describe tested configurations rather than project guarantees.

Semi-unitised, structural glazing and curved walls

Semi-unitised systems sit between the two. Mullions, and sometimes transoms, go up as sticks on site; factory-assembled, glazed frames or cassettes are then fixed into that grid. Glazing moves indoors while the frame keeps some site flexibility.

Some profile families serve more than one route. Reynaers offers a cassette-glazed variant of ConceptWall 86, in which glass is fitted into a frame and the frame is placed into a stick facade.

Structural glazing is a glazing method, not a build route. Glass bonded to the frame with structural silicone can be stick-built or unitised: Schüco’s AF UDC 80 SG is a structurally glazed unitised system, and Reynaers lists a structural glazed variant of ConceptWall 50. The facade engineer specifies the structural sealant and its design basis.

Curved curtain walls are usually faceted: flat panes or units meet at small angles at the mullions, so the curve is a series of straight segments within the joint angles each system permits. Bent glass gives a true curve but is a separate glass specification for the glass supplier to confirm. Ask for the system’s permitted angles before the elevation is fixed.

Curtain wall, window wall, storefront and cladding

The terms are often mixed up in tender documents. The difference is how each element meets the structure.

CriterionHow it meets the structureWhat it is
Curtain wallHangs outside the slab edges and runs continuously past the floorsNon-load-bearing glazed wall, built stick or unitised
Window wallSits between slabs, floor to soffit, one storey at a timeFramed glazing that stops at each slab, with the slab edge covered separately
StorefrontGround-floor framing between the floor and a headerShopfronts and entrances, usually on lighter framing
CladdingOpaque panels fixed to a subframe on the wallAluminium or composite rainscreen panels rather than glazing

In Dubai, the code’s thermal limits for glazed elements apply to the overall U-value, frame included (DBC 2021, E.5), so the profile system counts alongside the glass for every glazed type in this table.

Choosing a build route

Six questions settle most decisions. The more of them that point one way, the clearer the choice.

What we supply

Stick Curtain Wall

Mullions, transoms and components fabricated to your drawings and system. Labelling and packing for assembly on site by your team can be included in the quotation.

Unitised Panels

Units assembled and glazed in our factory to your drawings. Delivery to suit your installation sequence is agreed per project.

Send your facade drawings

Send elevations and sections, the system and series, wind-load and structural information from the engineer, the glass make-up, the finish specification, a BOQ or unit schedule and the installation programme. For unitised work, add the unit grid and the bracket and joint details. We price stick or unitised fabrication, or both where you want a comparison; for series data, see Schüco vs Reynaers.

Send drawings. Get a fabrication price.

Tell us what you need. Onos replies with questions or a written fabrication quotation, and never quotes for installation.

  1. Drawings: elevations, sections and the opening or panel schedule
  2. System and series, or the performance the specification asks for
  3. Finish, glass make-up and hardware
  4. Quantities or a BOQ, and the delivery emirate
  5. Programme: when you need fabricated units on site
  6. Who installs: your team or your nominated installer

Drawings and BOQs: [email protected]

We use your details only to reply to your request — see our privacy policy. Drawings or a BOQ can be emailed to [email protected].

Send drawings, a BOQ or quantities for a fabrication quote.

Request a Quote WhatsApp