Skip to content
Architectural plans with drafting pencils, a metal rule and tape

Technical Resources

Shop Drawings vs Fabrication Drawings

For contractors and installers on aluminium packages

The difference between shop drawings and fabrication drawings is who they are for. Shop drawings show the consultant how a specified aluminium or glazing system will be built and fixed on one project. Fabrication drawings are the factory’s own cutting, machining and assembly sheets, made from the approved shop drawings. Onos fabricates from the approved revision only, for contractors and installers in Dubai and across the UAE.

Once approved, shop drawings become the working reference for the package: other trades coordinate their interfaces against them, the fabricator produces cutting lists from them, the installer sets out and fixes the units from them, and each delivery is checked against their schedule marks.

What is the difference between shop drawings and fabrication drawings?

Shop drawings are submitted to show the consultant how the package will be built and fixed; fabrication drawings stay in the factory and tell it how to make each piece. Construction drawings, the third set, define what is to be built.

CriterionConstruction drawingsShop drawingsFabrication drawings
Prepared byThe architect and design engineersWhoever holds the shop-drawing scope: facade contractor, installer or fabricatorThe fabricator
PurposeDefine design intent, performance and appearanceShow how the chosen system meets the design on this projectInstruct the factory to cut, machine, assemble and glaze each item
Typical contentPlans, elevations, sections, typical details and the specificationUnit-by-unit elevations, profile sections, interfaces, fixings, glass make-ups, hardware, finishes and field-verified dimensionsCutting lists with lengths and angles, machining positions, and assembly and glazing sheets per schedule mark
Who signs offThe design team, which issues them for tender or constructionThe main contractor reviews, then the consultantThe fabricator, internally; not normally submitted
Used forTender, pricing and coordinationApproval, coordination with other trades, installationProduction and inspection
Level of detailTypical conditionsEvery condition on the projectEvery piece

Construction drawings are the design, shop drawings are the proposal for building it, and fabrication drawings are the factory’s instructions. Only the shop drawings go round the consultant’s approval loop.

Pencil and scale rule on a dimensioned technical drawing

Inputs for shop drawings

Shop drawings need the current design set plus the decisions that turn a design into a specific system. Whoever holds the shop-drawing scope needs all of it at the start: each missing item becomes a hold on the drawings, and holds become delays.

  • Issued-for-construction (IFC) drawings: plans, elevations, sections and typical details, at the current revision
  • The specification section for the aluminium and glazing works, including performance criteria and the submittal list
  • Window, door and partition schedules with types, sizes, opening directions and quantities
  • The system and series, or the performance it must meet if the choice is still open
  • Finish and colour references, glass make-ups and the hardware schedule
  • Structural criteria from the engineer: design wind pressure, deflection limits and other loads
  • Interface details: slab edges, openings, waterproofing, fixings and adjacent trades
  • Field-verified dimensions where the structure is built, and the planned installation sequence

How does the shop drawing approval process work?

Shop drawings go round a loop of submit, review, revise and resubmit until the consultant approves them. How long that takes depends on the size of the package, how complete the inputs are and how many review rounds are needed, so the programme should allow for revise-and-resubmit cycles.

  1. Register and plan

    List every drawing, calculation and sample in a submittal register, with planned submission dates tied to the programme.

  2. Prepare and check

    Drawings are prepared from the IFC set and checked against the specification, the system data and the other trades before they leave the drawing office.

  3. Contractor review

    The main contractor reviews and coordinates the submittal, then sends it to the consultant under a transmittal. The specification states who marks submittals and which documents need an engineer’s signature; UFGS 08 44 00, for example, asks for calculations signed and sealed by a professional engineer.

  4. Consultant review

    Each sheet comes back with a status such as approved, approved with comments, or revise and resubmit. The wording varies by consultant and contract.

  5. Revise and resubmit

    Comments are closed out on a new revision, with changes clouded and listed, until no comments remain open.

  6. Mock-up, where specified

    Some specifications give tentative approval before the mock-up and final approval only after it, as in this US curtain wall master specification, so final approval can wait for the mock-up.

  7. Release for fabrication

    The approved revision is issued to the fabricator, and cutting lists and fabrication sheets are produced from that revision only. We confirm our fabrication programme once the drawings and the approval route are known.

Revision control

Treat every revision as a controlled issue. Give each sheet a revision mark and date, cloud and list what changed, and record each issue and its status on a transmittal register, so everyone can see which revision is current.

At the fabricator, only the current approved revision should be in use. When a revision arrives after release for fabrication, cutting lists are reissued from it, anything already cut or assembled is checked against the change, and cost or programme effects are raised before work continues.

Aluminium package submittal contents

A submittal is the whole package sent for review, and shop drawings are one part of it. This is a typical list for an aluminium and glazing package; the project specification sets the actual one.

ItemWhat it usually contains
Supplier listProposed suppliers with model or catalogue numbers, specifications, inspection and test requirements, performance data and expected test dates (RAK QC guidelines)
Product dataSystem literature, technical data sheets and specifications for profiles, glass, gaskets, sealants and hardware
Shop drawingsThe system and its accessories, with field-verified dimensions shown on the drawings (VA 08 44 13)
CalculationsStructural and thermal calculations for the complete assembly, including deflection. The Dubai Building Code basis includes ASCE 7-16 loads, the Table E.1 deflection limits, ASTM E1300 for glass, ETAG 002 for structural silicone and an overall U-value that includes the frame
SamplesFinish and colour samples, and a corner sample showing fasteners, glazing and weather-stripping (VA 08 44 13)
Mock-upWhere specified: visual approval first, then performance tests, after which the approved mock-up is the standard for the works (UFGS 08 44 00, UL)
Component testsSealant compatibility and adhesion (ASTM C1087, C1135, C1401) and gaskets (ASTM C864), with time scheduled for testing (UFGS 08 44 00)
Quality documentsInspection and test plan and test results; the RAK guidelines ask for results at least 7 days before the material is built in (RAK QC guidelines)

The US federal templates (UFGS 08 44 00 and VA 08 44 13) are cited as examples of international submittal practice, not as UAE requirements. The RAK Municipality guidelines apply in Ras Al Khaimah. Your project specification governs.

Looking up at a glass curtain wall grid against a pale sky

Window and curtain wall shop drawings

Shop drawings for aluminium windows and doors are organised around the schedule: one elevation per type, with sizes, opening directions, hardware, glass make-up and finish, plus the head, sill and jamb details where the frame meets the structure and the waterproofing.

Curtain wall shop drawings add the grid: mullion and transom layout, splices and movement joints, brackets and anchors, and on a unitised system the stack and panel joints, with each panel numbered to the installation sequence. In Dubai, the structural calculations check deflection against Dubai Building Code Table E.1, which follows CWCT: for framing that holds insulating glass units, the limit is 1/175 of the span.

For the definitions, see stick vs unitised curtain wall; for panel fabrication, see unitised curtain wall.

Common causes of approval delay

Missing inputs and coordination between parties cause more delay than drafting time.

Releasing the approved set to the fabricator

Send it in a single issue: the approved revision with its review status, the transmittal, and the schedules at the same revision. A sheet still marked revise and resubmit, or a schedule one revision behind, delays fabrication rather than speeding it up.

Field-verified dimensions come from the party that controls the site, usually the main contractor or the installer, measured on the built structure and shown on the shop drawings. We fabricate and supply only, and make units to the dimensions on the approved revision, so confirm those dimensions before that revision is released.

Keep one reference per unit. When the schedule mark is the same on the shop drawings, the window and door schedule and the BOQ, it carries through to cutting lists, unit labels and delivery notes, and the site team can check each delivery against the drawings. Labelling by schedule mark can be included in our quotation; the fabrication page shows how an order runs.

Settle the scope split at tender. Shop drawings, structural calculations, samples and mock-up support can each sit with the facade contractor, the installer or the fabricator, so state in the RFQ who holds each item. We can price from tender or IFC drawings, the specification and schedules or a BOQ before shop drawings exist, and we list the system, finish, glass make-up and other assumptions priced on, so differences that appear as the drawings develop can be agreed before fabrication.

Send drawings for pricing

Send tender or approved drawings, the specification, schedules and a BOQ. We reply with clarifications or a written supply-only quotation that states its assumptions.

Send drawings. Get a fabrication price.

Tell us what you need. Onos replies with questions or a written fabrication quotation, and never quotes for installation.

  1. Drawings: elevations, sections and the opening or panel schedule
  2. System and series, or the performance the specification asks for
  3. Finish, glass make-up and hardware
  4. Quantities or a BOQ, and the delivery emirate
  5. Programme: when you need fabricated units on site
  6. Who installs: your team or your nominated installer

Drawings and BOQs: [email protected]

We use your details only to reply to your request — see our privacy policy. Drawings or a BOQ can be emailed to [email protected].

Send drawings, a BOQ or quantities for a fabrication quote.

Request a Quote WhatsApp